Contract No: HK/2009/05 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- december 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
13 January 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Table II Summary of
Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.11 Summary of submission status under
EP-356/2009 and FEP-05/356/2009 Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 4.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 4.7 Marine Water Quality Stations for
Additional DO Monitoring
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.9 Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract
no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.13 Water Monitoring Stations for Contract
no. HY/2009/15
Table 5.14 Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 5.15 Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting Month
Table 5.16 Details of Waste Disposal for Contract
no. HY/2009/11
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.18 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.19 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.4 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended
Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations, and Odour Patrol Results
Appendix
5.4 Water
Quality
Monitoring Results and Graphical Presentations
Appendix 5.4a Additional
Dissolved Oxygen Monitoring Results
Appendix
5.5 Real-time
Noise
Monitoring Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Summary for
Notification of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Reclamation
works;
¡P
Geo-textile
laying;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Installation of
berm blocks;
¡P
Concreting the
slopes of Open Channel U;
¡P
Construction of
in-situ mass concrete cooping;
¡P
Construction of
granite facing stone; and
¡P
Construction of
Seawall Type 8
¡P
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 1 & 2 sediment was
commences and substantially completed;
¡P
Removal of rock
armours from CH150 to CH180 at the North bank of HKCEC Water Channel was
commenced and substantially completed;
¡P
A trial for Type
3 sediment disposal was carried out;
¡P
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH170;
¡P
Installation of
precast RC outfall at Zone B1-3;
¡P
Trench
excavation for the 4 nos. of cooling water discharge pipes at B1-3;
¡P
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel;
¡P
Installation of
cross -harbour water mains nos. B13, A14/B14 and A15/ B15;
¡P
Thrust block
construction for A9/B9 and A11/B11 was commenced;
¡P
Concrete coating
at flange joint of cross-harbour water mains nos. A7B7/A8B8, A8B8/A9B9 and
A9B9/A10B10;
¡P
Rockfilling and
rock protection to cross-harbour watermains;
¡P
Installation of
pipe pile at TST (Land Portion) was commenced and substantially completed;
¡P
Grouting works
at TST seafront along the pipe piles have been installed;
¡P
Dredging of Type
2 sediment from CH50 to CH250 for subsequent cross-harbour watermains
installation off Tsim Sha Tsui;
¡P
Mainlaying works
at Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A, HKCEC Way In/Out, A2-3B
and A5-5;
¡P
Mainlaying works
at Zone B1-6, B2-2 and B1-5B;
¡P
Coring and
Grouting works for external wall of cooling pumping stations Nos. P4 & P5
at Zone B4-5;
¡P
Coring works for
external wall of cooling pumping station No P1 at Zone B4-2;
¡P
Mainlaying works
at Zone A1-5A1 and A3-5B;
¡P
Heading No. H4,
H5, H7 and H13;
¡P
Heading No. H3
was substantially completed.
¡P
GI duct laying
works at ZoneA4-3A and Zone A4-3B;
¡P
Trench
excavation, pipe laying works and chamber construction for a 1000 dia.
watermains (CHF) at Salisbury Garden
¡P
¡P
Concreting at Roof Plinth, lift shaft up to +14.15mPD and Fire Service
Pump room up to +14.15mPD of Passenger Terminal Building were completed;
¡P
E&M and ABWF of Passenger Terminal Building;
¡P
ELS of Noise Barrier 2 commenced on 29 Nov 2011 and nearly completed.
¡P
Casting of pedestrian pavement above seawall coping Bay 4 to Bay 8 was
completed on 13 December 2011;
¡P
Casting of the bus shelter footing at Expo Drive East was completed;
¡P
Precast slab installation at the existing movable ramp was in progress;
¡P
Saw cutting of existing slabs for the construction NB1 footing was
completed;
¡P
E&M of P7, P8 & P9
¡P
Approximate
¡P
Jacking pit at ex-pet garden for the heading construction of cooling
mains across Convention Avenue commenced;
¡P
Approximate
¡P
Construction of wash out chamber at Harbour Road and access manhole at Harbour
Centre were completed;
¡P
Trench excavation and cooling mains installation along Tonnochy Road;
¡P
Installation of PVC and G.I cable ducts was ongoing at Harbour Road;
¡P
Installation of submarine outfall pipe was completed;
¡P
Dredging for submarine outfall pipe was ongoing;
¡P
Concreting the Base Slab of Wan Shing Street at Bay 24 was completed;
¡P
Concreting the wall shaft and roof slab completed of Wan Shing Street at
Bay 21 and Bay 24 were completed;
¡P
Bay 21 to Bay 24 of Wan Shing Street were handover to HEC;
¡P
Slab at +3.10mPD and +3.77 mPD and wall below were completed for the WSD
Salt Water Pumping Station;
¡P
Excavation and lateral support for DSD receiving pits were completed;
¡P
D610 pipe pile wall construction at landside cofferdam of salt water
intake culvert;
¡P
12 out of 12 nos of pre-bored H-pile for box culverts N1 was casted as
of 21 November 2011;
¡P
Temporary working platform was completed and pile cap construction was
in progress at Portion 1B for the New Ferry Pier
¡P
Seawall block construction and reclamation work at TS4;
¡P
Night time protection works at CHT; and
¡P
Precautionary works at Abutment A
¡P
Installation of bored pile casing;
¡P
Excavation of bored piles; and
¡P
Concreting of bored piles
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C9 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
1 |
2 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
1 |
1 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
5 |
4 |
1 |
7 |
0 |
0 |
1 |
0 |
1 |
2 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
0 |
1 |
0 |
0 |
|
Total |
0 |
1 |
0 |
0 |
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/11- North Point Reclamation
¡P
The portion of
NPR3 are scheduled to be completed and handover in January 2012. No
construction work related to DP3 is anticipated to be conduced in coming month.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Reclamation of
HKCEC3W at the northern side within the HKCEC Water Channel would be continued;
¡P
Dredging from
CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be
resumed right after the consent from EPD for type 3 sediment has been received;
¡P
Rockfilling from
CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be
commenced;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH120 to CH170) would be
commenced;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH170 to CH260) would be
commenced;
¡P
Mainlaying works
for 4 nos. of cooling water discharge pipes at WC landfall section (B1-3) would
be completed. And subsequent reinstatement works was anticipated to be
completed be completed;
¡P
Dredging of type
3 sediment from CH50 to CH250 for subsequent cross-harbour watermains
installation off Tsim Sha Tsui would be continued right after the consent from
EPD has been received;
¡P
Ground treatment
works for the trenches excavation of the proposed cross-harbour watermains nos.
A18/b18 would be continued and anticipated to be completed;
¡P
Installation of
pipe pile wall at sea portion would be continued and anticipated to be
completed;
¡P
Thrust block
construction, concrete coating for flange joint and Rockfilling protection
works would be continued;
¡P
Works would be
continued at Zone A1-5A1, A2-3B, A3-3, A3-2A, A3-5B, A3-5B, A4-3A, A4-3B, HKCEC
way in/out, A5-5, B4-2, B4-5, B1-6 and B2-2;
¡P
GI duct laying
works at Zone A4-3A and A4-3 B would be completed;
¡P
Heading Nos. H4,
H5, H7 and H13 would be continued;
¡P
Heading Nos. H4
and H13 would be completed;
¡P
Heading No. H8 would
be commenced after its corresponding jacking pit at Zone A1-5A1 has been
excavated;
¡P
After the
completion of mainlaying works at Zone B4-2 and B4-5, mainlaying works at Zone
B4-4 would be commenced;
¡P
After the
completion of mainlaying works at HKCEC way in/out, mainlaying works at Zone
B4-2A would be commenced;
¡P
After the
completion of mainlaying works at A5-5, mainlaying works at Zone B5-2 would be
commenced.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Preparation
works for temporary diversion intakes of WSD salt water pumping station and Sun
Hung Kai pumping station.
¡P
Continue
operation of Tseung Kwan O Public Fill Sorting Facility;
¡P
Continue E&M
works and ABWF works of passenger terminal;
¡P
Complete
¡P
Complete excavation
works for noise barrier 2 at Expo Drive East;
¡P
Continue slab
modification for NB 1 footing at Expo Drive East;
¡P
Continue
construction for bus shelter at Expo Drive East;
¡P
Continue trench
excavation and pipe laying works along Harbour Road;
¡P
Continue trench
excavation and deck over at Tonnochy Road;
¡P
Continue
construction from +3.10mPD to + 5.17mPD for WSD Salt Water Pumping Station;
¡P
Complete
pipeline jacking WSD intake A;
¡P
Continue
construction of seaside cofferdams for salt water intake culvert, submarine
outfall and Box Culvert N1;
¡P
Commence
excavation works of landside cofferdam for the construction of Bay 6 ¡V 10 salt
water intake culvert;
¡P
Continue
backfilling rockfills for the installed submarine outfall pipes;
¡P
Continue
installation of the temporary water diversion steel frame;
¡P
Commence the
temporary internal propping works for Box Culvert O construction;
¡P
Continue
substructure works for the New Ferry Pier
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
¡P
Pumping test and
ELS preparation works at TPCWAE ;
¡P
Night time
protection works at CHT; and
¡P
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of
bored pile casing;
¡P
Excavation of
bored piles; and
¡P
Bored Pile Concreting
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th November to 27th
December 2011. The cut-off date of reporting is at 27th of each
reporting month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than 100
m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Mr. PL Yue |
9124 2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction Manager |
Mr. KK Yuen Mr. Andy Yu |
9498 1213 96484896 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658 3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Manager |
Mr. P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Construction Manager (East) |
Gene Cheung |
6105 4880 |
|
|
|
Construction Manager (West) |
Tony Chiu |
9090 0606 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
Reclamation works;
¡P
Geo-textile laying;
¡P
Slotted panel fixing;
¡P
Drainage Construction works;
¡P
Installation of berm blocks;
¡P
Concreting the slopes of Open Channel U;
¡P
Construction of in-situ mass concrete cooping;
¡P
Construction of granite facing stone; and
¡P
Construction of Seawall Type 8
2.4.4.
For Contract no. HK/2009/01, the principal work activities
in this reporting month included:
¡P
Dredging works within HKCEC Water Channel from CH190 to CH260 for Type 1
& 2 sediment was commences and substantially completed;
¡P
Removal of rock armours from CH150 to CH180 at the North bank of HKCEC
Water Channel was commenced and substantially completed;
¡P
A trial for Type 3 sediment disposal was carried out;
¡P
Installation of sheet pile for cooling water intake at Dome Promenade
between CH120 and CH170;
¡P
Installation of precast RC outfall at Zone B1-3;
¡P
Trench excavation for the 4 nos. of cooling water discharge pipes at
B1-3;
¡P
Reclamation of HKCEC3W (up to CH130) within HKCEC Water Channel;
¡P
Installation of cross -harbour water mains nos. B13, A14/B14 and A15/
B15;
¡P
Thrust block construction for A9/B9 and A11/B11 was commenced;
¡P
Concrete coating at flange joint of cross-harbour water mains nos.
A7B7/A8B8, A8B8/A9B9 and A9B9/A10B10;
¡P
Rockfilling and rock protection to cross-harbour watermains;
¡P
Installation of pipe pile at TST (Land Portion) was commenced and
substantially completed;
¡P
Grouting works at TST seafront along the pipe piles have been installed;
¡P
Dredging of Type 2 sediment from CH50 to CH250 for subsequent
cross-harbour watermains installation off Tsim Sha Tsui;
¡P
Mainlaying works at Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A,
HKCEC Way In/Out, A2-3B and A5-5;
¡P
Mainlaying works at Zone B1-6, B2-2 and B1-5B;
¡P
Coring and Grouting works for external wall of cooling pumping stations
Nos. P4 & P5 at Zone B4-5;
¡P
Coring works for external wall of cooling pumping station No P1 at Zone
B4-2;
¡P
Mainlaying works at Zone A1-5A1 and A3-5B;
¡P
Heading No. H4, H5, H7 and H13;
¡P
Heading No. H3 was substantially completed.
¡P
GI duct laying works at ZoneA4-3A and Zone A4-3B;
¡P
Trench excavation, pipe laying works and chamber construction for a 1000
dia. watermains (CHF) at Salisbury Garden
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
¡P
Concreting at Roof Plinth, lift shaft up to +14.15mPD and Fire Service
Pump room up to +14.15mPD of Passenger Terminal Building were completed;
¡P
E&M and ABWF of Passenger Terminal Building;
¡P
ELS of Noise Barrier 2 commenced on 29 Nov 2011 and nearly completed.
¡P
Casting of pedestrian pavement above seawall coping Bay 4 to Bay 8 was
completed on 13 December 2011;
¡P
Casting of the bus shelter footing at Expo Drive East was completed;
¡P
Precast slab installation at the existing movable ramp was in progress;
¡P
Saw cutting of existing slabs for the construction NB1 footing was
completed;
¡P
E&M of P7, P8 & P9
¡P
Approximate
¡P
Jacking pit at ex-pet garden for the heading construction of cooling
mains across Convention Avenue commenced;
¡P
Approximate
¡P
Construction of wash out chamber at Harbour Road and access manhole at Harbour
Centre were completed;
¡P
Trench excavation and cooling mains installation along Tonnochy Road;
¡P
Installation of PVC and G.I cable ducts was ongoing at Harbour Road;
¡P
Installation of submarine outfall pipe was completed;
¡P
Dredging for submarine outfall pipe was ongoing;
¡P
Concreting the Base Slab of Wan Shing Street at Bay 24 was completed;
¡P
Concreting the wall shaft and roof slab completed of Wan Shing Street at
Bay 21 and Bay 24 were completed;
¡P
Bay 21 to Bay 24 of Wan Shing Street were handover to HEC;
¡P
Slab at +3.10mPD and +3.77 mPD and wall below were completed for the WSD
Salt Water Pumping Station;
¡P
Excavation and lateral support for DSD receiving pits were completed;
¡P
D610 pipe pile wall construction at landside cofferdam of salt water
intake culvert;
¡P
12 out of 12 nos of pre-bored H-pile for box culverts N1 was casted as
of 21 November 2011;
¡P
Temporary working platform was completed and pile cap construction was
in progress at Portion 1B for the New Ferry Pier
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Seawall block construction and reclamation work at TS4;
¡P
Night time protection works at CHT; and
¡P
Precautionary works at Abutment A
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Installation of bored pile casing;
¡P
Excavation of bored piles; and
¡P
Concreting of bored piles
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
The portion of
NPR3 are scheduled to be completed and handover in January 2012. No
construction work related to DP3 is anticipated to be conduced in coming month.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Reclamation of
HKCEC3W at the northern side within the HKCEC Water Channel would be continued;
¡P
Dredging from
CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be
resumed right after the consent from EPD for type 3 sediment has been received;
¡P
Rockfilling from
CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be
commenced;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH120 to CH170) would be
commenced;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH170 to CH260) would be commenced;
¡P
Mainlaying works
for 4 nos. of cooling water discharge pipes at WC landfall section (B1-3) would
be completed. And subsequent reinstatement works was anticipated to be
completed be completed;
¡P
Dredging of type
3 sediment from CH50 to CH250 for subsequent cross-harbour watermains
installation off Tsim Sha Tsui would be continued right after the consent from
EPD has been received;
¡P
Ground treatment
works for the trenches excavation of the proposed cross-harbour watermains nos.
A18/b18 would be continued and anticipated to be completed;
¡P
Installation of
pipe pile wall at sea portion would be continued and anticipated to be
completed;
¡P
Thrust block
construction, concrete coating for flange joint and Rockfilling protection
works would be continued;
¡P
Works would be
continued at Zone A1-5A1, A2-3B, A3-3, A3-2A, A3-5B, A3-5B, A4-3A, A4-3B, HKCEC
way in/out, A5-5, B4-2, B4-5, B1-6 and B2-2;
¡P
GI duct laying
works at Zone A4-3A and A4-3 B would be completed;
¡P
Heading Nos. H4,
H5, H7 and H13 would be continued;
¡P
Heading Nos. H4
and H13 would be completed;
¡P
Heading No. H8 would
be commenced after its corresponding jacking pit at Zone A1-5A1 has been
excavated;
¡P
After the
completion of mainlaying works at Zone B4-2 and B4-5, mainlaying works at Zone
B4-4 would be commenced;
¡P
After the
completion of mainlaying works at HKCEC way in/out, mainlaying works at Zone
B4-2A would be commenced;
¡P
After the
completion of mainlaying works at A5-5, mainlaying works at Zone B5-2 would be
commenced.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Preparation
works for temporary diversion intakes of WSD salt water pumping station and Sun
Hung Kai pumping station.
¡P
Continue
operation of Tseung Kwan O Public Fill Sorting Facility;
¡P
Continue E&M
works and ABWF works of passenger terminal;
¡P
Complete
¡P
Complete excavation
works for noise barrier 2 at Expo Drive East;
¡P
Continue slab
modification for NB 1 footing at Expo Drive East;
¡P
Continue
construction for bus shelter at Expo Drive East;
¡P
Continue trench
excavation and pipe laying works along Harbour Road;
¡P
Continue trench
excavation and deck over at Tonnochy Road;
¡P
Continue
construction from +3.10mPD to + 5.17mPD for WSD Salt Water Pumping Station;
¡P
Complete
pipeline jacking WSD intake A;
¡P
Continue
construction of seaside cofferdams for salt water intake culvert, submarine
outfall and Box Culvert N1;
¡P
Commence
excavation works of landside cofferdam for the construction of Bay 6 ¡V 10 salt
water intake culvert;
¡P
Continue
backfilling rockfills for the installed submarine outfall pipes;
¡P
Continue
installation of the temporary water diversion steel frame;
¡P
Commence the
temporary internal propping works for Box Culvert O construction;
¡P
Continue substructure
works for the New Ferry Pier
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
ELS works at TS1;
¡P
Pumping test and
ELS preparation works at TPCWAE ;
¡P
Night time
protection works at CHT; and
¡P
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of
bored pile casing;
¡P
Excavation of
bored piles; and
¡P
Bored Pile
Concreting
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
3.1.4.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative
Summary of Valid Licences and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
331892 |
4 Jul. 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0922-11 |
12 Oct 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0680-11 |
22 Jul 2011 |
29 Jul 2011 to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Cancelled |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Valid |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0683-11 |
26 Sept 2011 |
20 Sept 2011 to 19 Mar 2012 |
Cancelled |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov 2011 |
27 Nov 2011 to 26 May 2012 |
Valid |
|
GW-RS1031-11 |
3 Nov 2011 |
7 Nov 2011 to 6 May 2012 |
Valid |
|
GW-RS1227-11 |
30 Dec 2011 |
30 Dec 2011 to 26 Jun 2012 |
To be valid on 30 Dec 2011 |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-091 |
23 Nov 2011 |
24 Nov 2011 to 23 May 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/12-085 |
4 Nov 2011 |
8 Nov 2011 to 7 Dec 2011 |
Expired |
EP/MD/12-099 |
7/12/2011 |
8 Dec 2011 to 7 Jan 2012 |
Valid |
|
EP/MD/12-097 |
1 Dec 2011 |
1 Dec 2011 to 30 Dec 2011 |
Valid till 30 Dec 2011 |
|
Permit for Dumping at Sea - Dredged Sediment Requiring
Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers |
EP/MD/12-094 |
19/12/2011 |
20 Dec 2011 ¡V 19 Jan 2011 |
Valid |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt
Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for
Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for
Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains |
15 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around Hong Kong
Exhibition and Convention Centre) |
15 May 2010 |
Landscape Plan (Night-time
Lighting) |
22 Oct 2010 |
|
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.6.
Summary of the current
status on licences and/or permits on environmental protection pertinent and
submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table
3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0011-11 |
27 April
2011 |
1 June 2011 to 30 Nov 2011 |
Expired |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0496-11 |
31 May 2011 |
07 Jun 2011 to 06 Dec 2011 |
Expired |
GW-RS0502-11 |
8 Jun 2011 |
13 Jun 2011 to 12 Dec 2011 |
Expired |
|
|
GW-RS0579-11 |
22 June 2011 |
17 July 2011 to 16 Jan 2012 |
Valid |
|
GW-RS0649-11 |
22 July 2011 |
1 Aug 2011 to 31 Jan 2012 |
Valid |
|
GW-RS0716-11 |
2 Aug 2011 |
12 Aug 2011 to 11 Feb 2012 |
Valid |
|
GW-RS0723-11 |
12 Aug 2011 |
15 Aug 2011 to 14 Feb 2012 |
Valid |
|
GW-RS0833-11 |
8 Sept 2011 |
10 Sept 2011 to 4 Mar 2012 |
Valid |
|
GW-RE0710-11 |
30 Sept 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
|
GW-RS0918-11 |
7 Oct 2011 |
10 Oct 2011 to 9 Apr 2012 |
Valid |
|
GW-RS0929-11 |
7 Oct 2011 |
10 Oct 2011 to 9 Apr 2012 |
Cancelled |
|
GW-RS0930-11 |
11 Oct 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct 2011 |
10 Oct 2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct 2011 |
23 Nov 2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct 2011 |
23 Nov 2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct 2011 |
18 Nov 2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct 2011 |
26 Oct 2011 to 23 April 2012 |
Valid |
|
GW-RS0984-11 |
25 Oct 2011 |
30 Oct 2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov 2011 |
7 Dec 2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov 2011 |
21 Nov 2011 to 18 May 2012 |
Valid |
|
GW-RS1111-11 |
25 Nov 2011 |
29 Nov 2011 to 28 May 2012 |
Valid |
|
GW-RS1116-11 |
28 Nov 2011 |
13 Dec 2011 to 12 Jun 2012 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 May 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 Apr 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste
Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
|
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-012 |
6 May 2011 |
29 May 2011 to 28 Nov
2011 |
Expired |
EP/MD/12-082 |
31 Oct 2011 |
29 Nov 2011 to 28 May
2012 |
Valid |
|
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-086 |
31 Oct 2011 |
10 Nov 2011 to 9 Dec 2012 |
Expired |
EP/MD/12-100 |
5 Dec 2011 |
10 Dec 2011 to 9 Jan 2012 |
Valid |
Table
3.7 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 1.12 |
Commencement Date of
Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main
Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location
Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
Rev. I |
17 Nov 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
|
Supplementary Information for
Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
Condition 2.12 (d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains |
19 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Combined
Version) |
5 Aug 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
3.1.7.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HY/2009/15 under EP-356/2009 are shown in Table 3.8 and
Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0820-11 |
5 Sep 2011 |
8 Sep 2011 to 7 Mar 2012 |
Valid |
|
GW-RS0847-11 |
14 Sep 2011 |
19 Sep 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS0858-11 |
16 Sep 2011 |
18 Sep 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS0883-11 |
4 Oct 2011 |
5 Oct 2011 to 4 Apr 2012 |
Valid |
|
GW-RS0997-11 |
2 Nov 2011 |
2 Nov 2011 to 2 May 2012 |
Valid |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
|
GW-RS1138-11 |
7 Dec 2011 |
8 Dec 2011 to 21 May 2012 |
Valid |
|
GW-RS1153-11 |
9 Dec 2011 |
12 Dec 2011 to 16 Mar 2012 |
Valid |
|
GW-RS1211-11 |
22 Dec 2011 |
24 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS1149-11 |
6 Dec 2011 |
8 Dec 2011 to 7 Jun 2012 |
Valid |
|
GW-RS1190-11 |
30 Dec 2011 |
22 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS1212-11 |
28 Dec 2011 |
28 Dec 2011 to 19 Jun 2012 |
To be valid on 28 Dec 11 |
Registration as a Chemical
Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Water Discharge Licence |
WT00008780-2011 |
22 Mar 2011 |
22 Mar 2011 to 31 Mar 2016 |
Valid |
|
WT00010482-2011 |
30 Sep 2011 |
30 Sep 2011 to 30 Sep 2013 |
Valid |
|
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011 to 31 Dec 2013 |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Dumping by
Vessel) |
7011761 |
12 Oct 2011 |
31 Oct 2011 to 31 Jan 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-037 |
20 Jul 2011 |
20 Jul 2011 to 19 Jan 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-084 |
31 Oct
2011 |
1 Nov 2011 to 30 Nov 2011 |
Expired |
EP/MD/12-096 |
29 Nov 2011 |
1 Dec 2011 to 31 Dec 2011 |
Valid till 31 Dec 2011 |
|
Dumping Permit (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
EP/MD/12-089 |
8 Nov 2011 |
10 Nov 2011 to 9 Dec 2011 |
Expired |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 |
Amendment for Works Schedule
and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
Rev 2 |
11 May 2011 |
Condition 2.9 |
Silt Screen Deployment Plan
Rev3 |
15 Jun 2011 |
Condition 2.18 |
Amendment for Proposal for the
Removal of Odorous Sediment and Slime |
2 Aug 2011 |
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Amendment for Noise Management
Plan |
27 Jan 2011 |
3.1.8.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 3.1.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.9.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no. HK/2010/06
under EP-356/2009 are shown in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0605-11 |
29 Jun
2011 |
13 Jul 2011 to 12 Jan 2012 |
Valid |
|
GW-RS0879-11 |
22
Sept 2011 |
6 Oct
2011 to 5 Apr 2012 |
Valid |
Billing Account under Waste Disposal Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Water Discharge Licence |
WT00010905-2011 |
4 November 2011 |
31 July 2016 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-030 |
11 Aug 11 |
12 Aug 2011 to 11 Feb 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-088 |
8 Nov
2011 |
12 Nov
2011 to 11
Dec 2011 |
Expired |
EP/MD/12-102 |
8 Dec
2011 |
12 Dec
2011 to 11 Jan
2012 |
Valid |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of
Main Construction Companies |
24 October 2011 |
Condition 2.7 |
Works Schedule and Location
Plans |
11 March 2011 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan |
31 Aug 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
11 April 2011 |
Condition 2.23 |
Noise Management Plan |
11 March 2011 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
Real-time Noise Monitoring Stations
4.1.2.
The real-time noise monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin
Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise
level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on
normal weekdays. For all other time periods, Leq (5 minutes) shall
be employed for comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
one set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.5.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.6.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1)
specifications shall be used for carrying out the noise monitoring. Immediately
prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency. Measurements may be accepted as valid only
if the calibration level from before and after the noise measurement agree to
within 1.0 dB.
4.1.7.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
CWB PRE
Site Office * |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
WDII PRE
Site Office * |
Wan Chai |
* Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6 - 1.7 m3 per
minute adjustable flow range;
¡P
equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
¡P
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable of
providing a minimum exposed area of 406 cm2;
¡P
flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped with a
shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped with a
flow recorder for continuous monitoring;
¡P
provided with a
peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able to hold and
seal the filter paper to the sampler housing at horizontal position;
¡P
easily
changeable filter; and
¡P
capable of
operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS
accredited laboratory was set-up for carrying out
the laboratory analysis, the laboratory equipment was approved by the ER
on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results.
4.2.9.
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for odour patrol
4.2.12. Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
¡P
be at least 16
years of age;
¡P
be free from any
respiratory illnesses; and
¡P
not be allowed
to smoke, eat, drink (except water) or use chewing gum or sweets 30 min
¡P
before and
during odour patrol
4.2.13. Odour
patrol shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
4.2.14. The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be
affected by the odour nuisance will be identified.
4.2.15. The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
¡P
0 - Not
detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 - Slight
Identifiable odour, and slight chance to have odour nuisance;
¡P
2 - Moderate
Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 - Strong
Identifiable, likely to have odour nuisance;
¡P
4 - Extreme
Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.
4.2.17.
The qualified odour patrol member has individual
n-butanol thresholds complied with the requirement of European Standard Method
of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry
(EN13725) in the range of 20 to 80 ppb. The certificate for the qualified odour
panel member is shown in Appendix
4.2.
4.3.1.
The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality monitoring for dissolved oxygen (DO),
suspended solid (SS) and turbidity is therefore recommended to be carried out
at selected WSD flushing water intakes. The impact monitoring should be carried
out during the proposed dredging works to ensure the compliance with the water
quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April ¡V September) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
It is proposed to monitor the water quality at 9
WSD salt water intakes and 12 cooling water intakes along the seafront of the
Victoria Harbour. The proposed water quality monitoring stations of the Project
are shown in Table 4.4 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW21 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great Eagle
Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great Eagle
Centre (Western) |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior
Hotel |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
Windsor House (Temporary Dilution) |
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
4.3.5.
In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table
4.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ measurements and water sampling should be carried
out in each sampling event. For selection of tides for in-situ measurement and
water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement and water
sampling, tidal range of individual flood and ebb tides should be not less than
0.5m.
2.
Turbidity should be measured in situ whereas SS should be
determined by laboratory.
Dissolved Oxygen and Temperature Measuring
Equipment
4.3.7.
The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
¡P
a dissolved
oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a temperature of
0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring turbidity
between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an
approved similar instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).
Sample Container and Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
4.3.16. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when necessary. Backup
monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance, calibration,
etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix
4.2.
Laboratory Measurement / Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure 4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
Windsor
House |
Ex-WPCWA-SW |
South-western of the ex-Wan Chai Public Cargo
Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai Public Cargo
Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of
suspended solids and 24 hour monitoring of turbidity at the cooling water
intakes (C6 and C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water quality
monitoring station in front of the intakes during the dredging activities. The
monitoring system include the turbidity sensor and data logger which is capable
of data capturing at every 5 minutes. The data sahll be downloaded daily and
compared with the Action and Limit level determined during the baseline water
qualtiy monitoring at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension could
be continuously monitored.
4.3.27. The
proposed DO monitoring stations of the Project are shown in Table 4.7 and
Figure 4.1.
Table
4.7 Marine Water
Quality Stations for Additional DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
4.3.28. The
monitoring of dissolved oxygen are to be carried out once per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall
layout showing work areas of various contracts, latest status of work
commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point
Reclamation;
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre; and
Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass over MTR Tsuen Wan Line
5.0.3.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.1.1.
The proposed division of noise monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
5.1.2.
Day time and evening period noise monitoring was
conducted at the City Garden and Victoria Centre in the reporting month.
5.1.3.
Noise monitoring results measured in this reporting
period are reviewed and summarized. No exceedance was recorded in reporting
month. Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.4.
The proposed division of noise monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.5.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
5.1.6.
Two limit level exceedances were recorded at M1a -
Harbour Road Sports Centre on 29 November and 6 December 2011 during restricted hour. Major noise source was
contributed from Tonnochy Road and water sport competition at Wan Chai Training
Swimming Pool.
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.1.7.
The noise monitoring for HY/2009/15 was commenced
on 10 November 2010. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.8.
Noise monitoring results measured in the period of
daytime and restricted hour are reviewed and summarized. No exceedance was
recorded in reporting month.Details of noise monitoring results and graphical
presentation can be referred in Appendix
5.2.
5.2.1.
No
construction activity was conducted during night time period (2300 to 0700) in
this reporting month.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.2.2.
The proposed divisions of real-time noise
monitoring stations are summarized in Table 5.4 below. Real time
noise monitoring for the filling works under contract no. HY/2009/11 was
commenced on 5 October 2010.
Table 5.4 Real
Time Noise Monitoring Station for Contract no. HY/2009/11
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitefield
Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
*
Real time noise monitoring results and graphical presentation during night time
period are for information only.
5.2.3.
Real time noise monitoring results were reviewed
and no project-related Action and
Limit level exceedance were recorded in the reporting period. Details of
real time noise monitoring results and graphical presentation can be referred
to Appendix 5.5.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.3.1.
The major construction activity of Contract no.
HY/2009/11 was filling works in the reporting month. Air monitoring had been
commenced on 11 August 2010. The proposed division of air monitoring stations is
summarized in Table 5.5 below.
Table 5.5 Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
5.3.2.
No exceedance was recorded in the reporting month.
Details of air monitoring results and graphical presentation can be referred in
Appendix 5.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.3.
Air monitoring was commenced on 1 April 2011 in response
to the commencement of the land-filling work for Contract no. HK/2009/01. The
proposed division of air monitoring stations are summarized in Table 5.6
below. No exceedance was recorded in the reporting month.
Table 5.6 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.4.
Air monitoring was commenced in mid-January 2011
for the land-filling work for Contract no. HK/2009/02. The proposed division of
air monitoring stations are summarized in Table 5.7 below. No
exceedance was recorded in the reporting month.
Table 5.7 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.3.5.
Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air
monitoring stations are summarized in Table 5.8 below. No
exceedance was recorded in the reporting month.
Table
5.8 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.4.1
Due to unavailability of the access of WSD7, no water quality monitoring
was conducted on 28 November 2011 at mid-ebb and on 17 December 2011 at
mid-ebb.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.4.1.
The proposed division of water monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.9 below:
Table 5.9 Water Monitoring Stations for Contract no. HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.2.
Water monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.10 below.
Table 5.10 Water
Monitoring Stations for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great
Eagle Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great
Eagle Centre (Western) |
835629.8 |
815889.2 |
Remarks:
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.3.
Water monitoring for Contract no. HK/2009/02 was
commenced on 8 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.11 below.
Table 5.11 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
Cooling Water Intake |
|||
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
Remarks:
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
5.4.4.
Water monitoring for Contract no. HK/2010/06 was
commenced on 8 March 2011. The proposed division of water monitoring stations
are summarized in Table 5.12 below.
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.4.5.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was
commenced on 9 November 2010. The proposed division of water monitoring
stations are summarized in Table 5.13 below.
Table 5.13 Water
Monitoring Stations for Contract no. HY/2009/15
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
5.4.6.
The
enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was
commenced on 13 January 2011. No project-related exceedance was recorded in the daily SS
monitoring and 24 hours turbidity monitoring.
5.4.7.
As
per the meeting with the representative of Excelsior Hotel and World Trade
Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011.
5.4.8.
The dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter was resumed on 26 October
2011,
daily monitoring of suspended solids and 24 hours monitoring of turbidity at
the cooling water intakes at C7 was conducted. With
respect to the seawall collapsing at TS4 on 17 November 2011, the 24 hours turbidity
monitoring and daily SS was kept in November and December 2011. As there was no adverse impact on the SS results
obtained during the period of seawall collapse, the daily SS monitoring at C7
was then suspended on 23 December 2011. The 24hr turbidity monitoring will be
kept to monitor until the completion of reinstating the seawall at TS4.
5.4.9.
Water monitoring results measured in this reporting
period are reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix
5.4.
Table 5.14 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C9 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
1 |
2 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
1 |
1 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
5 |
4 |
1 |
7 |
0 |
0 |
1 |
0 |
1 |
2 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
5.4.10. Enhanced DO monitoring at 4
monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works
Area was conducted three days per week during the reporting period. The action
and limit level exceedances of water quality monitoring are summarized in Table 5.15.
Table 5.15 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
C6 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
0 |
1 |
0 |
0 |
|
Total |
0 |
1 |
0 |
0 |
5.4.11.
Investigations were found that the exceedances are
not related to the Project works. The details of the recorded excedances can be
referred to the Section 6.3.
5.4.12. In response to the Condition 2.18
of the Environmental Permit no. EP-356/2009 requiring that a silt curtain /
impermeable barrier system be installed to channel water discharge flow from
Culvert L to locations outside the embayment area, a proposed replacement of
the requirement with additional dissolved oxygen monitoring has been conducted
at three monitoring stations, namely A, B and C between the eastern seawall of
Central Reclamation Phase III and the HKCEC Extension since November 2011 under
EP-356/2009 so that DO level between the eastern seawall of Central Reclamation
Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be
referred in Appendix
5.4a.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.5.1.
Non-inert C&D waste was disposed of in the
reporting month. Details of the waste flow table are summarized in Table
5.16.
Table
5.16 Details of
Waste Disposal for Contract no. HY/2009/11
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
73.13 |
692.255 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
N/A |
N/A |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
89,500 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
129,200 (Bulk Volume) |
East of Sha Chau |
5.5.2.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
5.5.3.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.17.
Table 5.17 Details of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
536.01 |
12,402.61 |
TKO137, TM38 |
Inert
C&D materials recycled, m3 |
0 |
389.96 |
N/A |
Non-inert
C&D materials disposed, m3 |
29.72 |
534.28 |
|
Non-inert
C&D materials recycled, kg |
8,570 |
135,491 |
N/A |
Chemical
waste disposed, kg |
220 |
5,350 |
N/A |
*Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
83,482.2 (Bulk Volume) |
South of Cheung Chau |
* Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
2,786 (Bulk Volume) |
20,516 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal contained
in Geosynthetic Containers |
0 (Bulk Volume) |
257 (Bulk Volume) |
East of Cha Chau |
5.5.4.
There were marine sediments Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal in the
reporting month. The maximum dredging rate in cross harbour water main and
HKCEC3w are 539m3 and 502 m3 per day respectively, which is
complied with the recommended maximum dredging rate listed in Table 2 of FEP-02/356/2009.
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
5.5.5.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.18.
Table
5.18 Details of
Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
5,239 |
58,975 |
TKO137 / TM 38 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
35 |
294 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
0 |
2,115 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
332 (Bulk volume) |
154,827 (Bulk volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 |
110,632 (Bulk volume) |
East of Sha Chau |
*Remarks: Contractor clarified that the cumulative
quantities of marine sediments (Type 1 ¡V Open Sea Disposal) should be 152,871m3
in October 2011.
5.5.6.
There was marine sediments Type 1 ¡V Open Sea
Disposal disposed in the reporting month. The maximum dredging rate in submarine
sewage pipelines is 332m3 per day respectively, which is complied
with the recommended maximum dredging rate, 1500m3 per day listed in
Table 2 of FEP-02/356/2009.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
5.5.7.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/15
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
3,220.7 |
61,769.4 |
Tuen Mun Area 38 |
310.4 |
876.7 |
TKO137 FB |
|
Inert
C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
NIL |
304 |
ex-PCWA |
|
0 |
109 |
TS4 |
|
Non-inert
C&D materials disposed, m3 |
10.8 |
154.4 |
SENT Landfill |
Non-inert
C&D materials recycled, kg |
150 |
13,965 |
N/A |
Chemical
waste disposed, kg |
2,200 |
8,000 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
33,427 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
158,812 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
0 (Bulk Volume) |
7,050 (Bulk Volume) |
East of Sha Chau |
5.5.8.
In
the reporting month, there was no marine sediment disposed of in reporting month.
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass over MTR Tsuen Wan Line
5.5.9.
Inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details of Waste Disposal for Contract no. HK/2010/06
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
1745.4 |
4914.9 |
TM38 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled, kg |
57.5 |
57.5 |
N/A |
Chemical
waste disposed, L |
0 |
600 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
385 (Bulk Volume) |
3,042 (Bulk Volume) |
South Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
536 (Bulk Volume) |
(Bulk Volume) |
East Sha Chau |
5.5.10. There were
marine sediments Type 1 ¡V Open Sea Disposal and Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal dredging from bore-piling casing in the reporting
month.
6.0.1.
The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 6.1.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.1.1.
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.1.2.
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.1.3.
Two limit level exceedances were recorded at M1a -
Harbour Road Sports Centre on 29 November and 6 December 2011
during restricted hour. Major noise source was
contributed from Tonnochy Road and water sport competition at Wan Chai Training
Swimming Pool. The construction works were complied with the conditions under
valid Construction Noise Permits during the measurement.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
6.1.4.
No exceedance was recorded in the reporting month.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.1.5.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.2.1.
No
project-related exceedance was recorded in the reporting month.
6.3.1.
No exceedance was recorded in the TSP monitoring in
the reporting month.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.4.1.
There were occasionally turbidity and SS exceedances
at mid-flood were recorded at WSD15, C8 and C9 in this reporting month.
Investigation revealed that there are numerous unknown outfalls from the nearby
coastal area closed to the cooling intakes C8 and C9, it causes the potential
for accumulation of pollutants near the intakes and may lead to potential water
quality deterioration at the seawater intake points. Investigation revealed
that the SS exceedance at WSD15 was located in upstream of the Project during flood
tide and the water quality at monitoring stations located nearest the marine
work site were well below the Action level.
6.4.2.
Contractor¡¦s marine activities were checked and proper
condition of silt curtain was provided between the barge and the seawall during
the filling material transportation. The recorded turbidity and SS exceedances
were considered as not project-related.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.4.3.
Exceedances
of turbidity and SS level were recorded at WSD7, WSD19 and WSD20. Checked with
Contractor's works, the deployed silt screen and silt curtain were in proper
condition for the works of sheet pile wall at Tsim Sha Tsui and dredging at Cross
Harbour Water Main. In view that the silt screen and silt curtain were in
proper condition, these exceedances were considered no related to Project work.
6.4.4.
One
SS exceedance at C3 was recorded on 17 December 2011. Investigation revealed
that the frame type silt screen at the intake and silt curtain along the HKCEC
water channel and rock bund were deployed properly. Other than that, Contractor's
daily records were checked and no further exceedance was recorded in the next
consecutive monitoring. Thus, it was concluded not Project related exceedances.
6.4.5.
One
SS exceedance at C4 e on 28 November 2011 and one SS exceedance at C4w on 26
December 2011 were recorded in this reporting month. Checking with Contractor works, there was
no marine works in HKCEC water channel at that night. Other than that,
Contractor's inspection records were checked. It shows silt screens and curtains
were deployed in proper condition. It was concluded that these exceedances were
not related to the Project works.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.4.6.
There were one turbidity and one SS level
exceedance recorded at C5e on 28 November and one SS level exceedances recorded
at C5w on 9 December 2011. Contractor marine work activities and mitigation
measures were checked, deployed silt screen at intake and silt curtain at
western temporary sheet pile were observed in proper condition during the water
quality monitoring. During the water monitoring events on these two days, fine
floating particles was observed near the intakes and inside the silt screen.
Contractor was reminded to increase the frequency of removal of floating debris
and fine particles near the intakes whenever it is necessary. It was concluded
that these exceedances were not related to the Project works.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)
6.4.7.
One
DO level exceedances was recorded at ex-WPCWA SE was recorded on 23 December
2011. Checked Contractor¡¦s works, there was no marine work conducted in
ex-WPCA. These exceedances were
considered as the natural variation and not related to the Project works.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.8.
No exceedance was recorded in the reporting month.
6.4.9.
Summary for notification of exceedances can be
referred to Appendix
6.2.
6.5.1.
There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.6.1.
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
From the Monthly EM&A report (November 2011) of Central Reclamation
Phase III the key works in December 2011 are as follows:
¡P
Type A filling in FRAW and FRAE above +2.5mPD
¡P
General filling works above +2.5mPD in IRAE
¡P
Surcharging in FRAW and FRAE
¡P
Construction of GPO boundary wall
¡P
Construction of PLA boundary wall
¡P
Construction of Promenade enhancement works
¡P
Construction of buildings at PLA berth
¡P
Installation of cooling mains discharge pipes in FRAE and FRAW
¡P
Backfilling of CWB structure
¡P
Importation of fill material
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the reclamation works at NPR2E,
dredging and filling at HKCEC3w, dredging at submarine sewage pipelines, reinstatement
of seawall block construction at TCBR1W and marine bored piling at MTR Tunnel
Crossing in the reporting month. The major environmental impact was water
quality impact at North Point, Causeway Bay and Wan Chai.
7.0.4.
The major environmental impacts generated from the
filling work at Central Reclamation Phase III were only located along the
coastline of Central and Admiralty. As no project related exceedance was
recorded in the Project, it was considered no adverse environmental impact
caused by the Project works. Thus, it is evaluated the cumulative construction
impact from the concurrent projects including Wan Chai Development Phase II and
Central Reclamation Phase III was insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HY/2009/11, HK/2009/01, HK/2009/02,
HY/2009/15 and HK/2010/06. No non-conformance was identified during the site
audits.
8.0.2.
Four site inspections for Contract no. HY/2009/11
were carried out on 28 November, 6, 13 and 20 December 2011. The results of
these inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections
for Contract no. HY/2009/11
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111128_01 |
28-Nov-11 |
Water ponding behind site office. |
Removal of water ponding |
Completion
as observed on 6 Dec 2011 |
111206_01 |
6-Dec-11 |
Floating
debris and refuse in U-channel. |
Removal of floating debris |
Completion
as observed on 13 Dec 2011 |
111206_02 |
6-Dec-11 |
Construction
runoff and drainage behind the site office. |
Avoid any runoff flow outside the site boundary |
Completion
as observed on 13 Dec 2011 |
111213_01 |
13-Dec-11 |
Water
spraying shall be conducted for earth works. |
Regular spraying water on the dry dust surface |
Completion
as observed on 20 Dec 2011 |
111213_02 |
13-Dec-11 |
Filling
materials near seafront shall be collected. |
Removal of the filling material near the seafront |
Completion
as observed on 20 Dec 2011 |
111220_01 |
20-Dec-11 |
Floating
debris and refuse near the sea in the eastern seawall (C27). |
Regular removal of the floating debris |
Completion
as observed on 28 Dec 2011 |
8.0.3.
Four site inspections for Contract no. HK/2009/01
were carried out on 30 November, 7, 14 and 21 December 2011. Results of these
inspections and outcomes are summarized in Table 8.2.
Table
8.2 Summary of
Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111130_01 |
30-Nov-11 |
Oil
stain on the bare ground at HKCCEC3w shall be proper cleared up and disposed
as chemical waste. |
Proper cleared up and disposed the oil
strain as
chemical waste |
Completion
as observed on 7-Dec-11 |
111130_02 |
30-Nov-11 |
Sand
bags along the site access at north-bound up of HKCEC shall be enhanced to
avoid spillage of wastewater out of site boundary. |
Replace the new sandbags |
Completion
as observed on 7-Dec-11 |
111207_01 |
7-Dec-11 |
Excavator
located Convention Avenue shall be repaired to avoid oil leakage. Beside, the
drip try next to the excavator shall be repaired. |
Repair the plant and drip tray |
Completion
as observed on 14-Dec-11 |
111207_02 |
7-Dec-11 |
The
tress at TST shall be regularly watered. |
Regular watering the trees |
Completion
as observed on 14-Dec-11 |
111214_01 |
14-Dec-11 |
Oil
leakage from crawler crane was found at HKCEC1. Maintenance work for this
plant shall be provided. The contaminated soil on the base ground shall be
removed and disposed with proper procedure. |
Repair the plant and collect the contaminated
soil and disposed with proper procedure |
Completion
as observed on 23-Dec-11 |
111221_01 |
21-Dec-11 |
Contaminated
soil at HKCEC1 shall be removed and handled as chemical waste. |
Collect the contaminated soil and disposed with
proper procedure |
Completion
as observed on 30-Dec-11 |
111221_02 |
21-Dec-11 |
The
edge of soil screen at HKCEC1 shall be maintained and improved. |
Maintained and improved the edge of soil screen |
Completion
as observed on 30-Dec-11 |
111221_03 |
21-Dec-11 |
The
deployed silt curtain adjacent to VIP drop off area shall be improved. |
Improve the silt curtain deployment |
Completion
as observed on 30-Dec-11 |
111221_04 |
21-Dec-11 |
The
soil found at the edge of TST shall be trimmed-off. |
Trimmed-off the soil at the edge |
Completion
as observed on 30-Dec-11 |
8.0.4.
Four site inspections for Contract no. HK/2009/02
were carried out on 1, 8, 15, 19 December 2011 during this reporting period. The
results of these inspections and outcomes are summarized in Table 8.3.
Table
8.3 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111201_01 |
1-Dec-11 |
Oil
leakage from an excavator was found at Wan Shing Street. Contractor shall
provide the maintenance work to the plant and remove contaminated soil as
chemical waste. |
Provide
the maintenance work to the plant and remove contaminated soil as chemical
waste. |
Completion
as observed on 8-Dec-11 |
111201_02 |
1-Dec-11 |
Worn
sand located at seafront near Sun Hung Kei intakes shall be replaced. |
Replace the new sandbags |
Completion
as observed on 8-Dec-11 |
111201_03 |
1-Dec-11 |
Drip
tray shall be placed underneath the oil containers at ex-pet Garden. |
Provide drip tray for chemical storage |
Completion
as observed on 8-Dec-11 |
111201_04 |
1-Dec-11 |
Contractor
was reminded that no wastewater shall be leaking from the truck during
transportation. |
Ensure the soil is dry enough before transport |
Completion
as observed on 8-Dec-11 |
111208_01 |
8-Dec-11 |
Oil
leakage was found from the crawler crane at ex-Pet Garden. Plants maintenance
shall be provided be contaminated soil shall be handle as chemical waste with
proper procedure. |
Repair the plant and collect the contaminated
soil and disposed with proper procedure |
Completion
as observed on 15-Dec-11 |
111208_02 |
8-Dec-11 |
Ponding
water shall be avoided to accumulate at the site near western seawall. |
Review and maintain a proper site drain |
Completion
as observed on 15-Dec-11 |
111208_03 |
8-Dec-11 |
Floating
fine particle near western seawall shall be removed. |
Remove the fine particle |
Completion
as observed on 15-Dec-11 |
111215_01 |
15-Dec-11 |
Permanent
protective measures shall be provided for the oil leakage plants if the
leakages could not be prevented. (Ex Pet Garden) |
Provide permanent protective measures to the oil
leakage plants |
Completion
as observed on 19-Dec-11 |
111215_02 |
15-Dec-11 |
C
and D materials inside drip tray shall be collected (Ex-Pet Garden). |
Collect the C&D materials. |
Completion
as observed on 19-Dec-11 |
111219_01 |
19-Dec-11 |
Maintenance
work shall be provided to the derrick barge («°³ù3) to avoid dark smoke emission. |
Provide maintenance work to the derrick barge |
Completion
as observed on 29-Dec-11 |
111219_02 |
19-Dec-11 |
Oil
drum located at Wan Shing Street shall be placed underneath the drip tray. |
Provide drip tray for chemical storage |
Completion
as observed on 29-Dec-11 |
8.0.5.
Four site inspections for Contract no. HY/2009/15
were carried out on 29 November, 6, 13 and 20 December 2011 in reporting month.
The results of these inspections and outcomes are summarized in Table
8.4.
Table
8.4 Summary of
Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action taken by Contractor |
Outcome |
|
111129_01 |
29-Nov-11 |
Silty water was observed slightly
leaking outside the silt curtain for the protection of seawall collapsed.
Investigation found that the seabed was distributed by compressed air for the
rectification works. The contractor should review the silt curtain and deploy
suitable silt curtain for the operation. |
Review the silt curtain and deploy suitable silt curtain
for the operation |
Completion as observed on 6-Dec-11 |
111129_02 |
29-Nov-11 |
Milky water was discharged at the
discharge point after treatment. The contractor was reminded to review the
efficiency of the system (TS1). |
Review the efficiency of the waste water treatment system |
Completion as observed on 6-Dec-11 |
111206_01 |
6-Dec-11 |
Drip tray shall be provided for
chemical storage (Ex-TPCWA). |
Provide drip tray for chemical storage |
Completion as observed on 13-Dec-11 |
111206_02 |
6-Dec-11 |
Packed cement bags shall be covered
by tarpaulin (Ex-TCPWA). |
covered packed cement bags by tarpaulin |
Completion as observed on 13-Dec-11 |
111213_01 |
13-Dec-11 |
Oil leakage from an oil drum was
observed at TS1. The contractor was reminded to provide drip tray and proper
label. Moreover, the oil need to be treated with proper treatment. |
Provide drip tray and proper label.
Moreover, the oil needed to be treated with
proper treatment. |
Completion as observed on 20-Dec-11 |
111220_01 |
20-Dec-11 |
Drip tray shall be provided for
chemical storage (TS1, ExTCPWA). |
provided for chemical storage |
Completion as observed on 29-Dec-11 |
111220_02 |
20-Dec-11 |
Floating refuse shall be collected
(TS1, TS4). |
Collect
floating refuses |
Completion as observed on 29-Dec-11 |
111220_03 |
20-Dec-11 |
Waste water from site cleaning
shall be collected and treated properly prior discharge (Entrance of CWB PRE
site office). |
Treat
and collect the surface runoff outside site boundary. |
Completion as observed on 29-Dec-11 |
111220_04 |
20-Dec-11 |
Sloping seawall shall be properly
protected by geotextile (TS4). |
Protect
the slopping seawall properly |
In
progress |
8.0.6.
Four site inspections for Contract no. HK/2010/06
were carried out on 28 November 2011, 5, 12 and 19 December in reporting month.
The results of these inspections and outcomes are summarized in Table
8.5.
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111205_01 |
5-Dec-11 |
Grease was observed inside the pile
at the side of western bored-pile staging. The contractor was reminded to
clear it with proper treatment. |
Removal
of the grease inside the pile |
Completion as observed on 12-Dec-11 |
111212_01 |
12-Dec-11 |
Silt was observed on the silt
curtain under the marine working platform. The contractor was reminded to
check the platform regularly to prevent any objects and silt from dropping
into the sea. |
Checked
and avoid any objects and silt dropping into the sea. |
Completion as observed on 19-Dec-11 |
111212_02 |
12-Dec-11 |
The end of the drainage for
collecting surface runoff should be sealed to prevent the surface runoff from
discharging into the sea directly. |
Sealed
the end of the drainage along the platform. |
Completion as observed on 19-Dec-11 |
111212_03 |
12-Dec-11 |
Proper label should be provided to
the containers inside the chemical waste storage area. |
Adhered
proper label on chemical waste. |
Completion as observed on 19-Dec-11 |
111219_01 |
19-Dec-11 |
Contractor was reminded to
regularly dispose the accumulated C&D waste which locates at derrick barge. |
Regular
disposal of the C&D waste |
Completion as observed on 30-Dec-11 |
9.0.1.
There was no complaint received in this reporting
month.
9.0.2.
The details of cumulative complaint log and updated
summary of complaints are presented in Appendix
9.1.
9.0.3.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
25 |
December 2011 |
0 |
Project-to-Date |
25 |
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
9.0.4.
Follow-up
the seawall blocks collapsing incident occurred at Tunnel Section 4, TS4
(within TCBR1W) under Contractor of HY/2009/15 in last reporting month, reinstatement
of Seawall Blocks Bay 5 and 6 were completed in reporting month. Remaining half
of Bay 4 seawall blocks will be completed in mid-Jan 2012. According to the RSS
reporting, inspection of silt curtains were carried out once every week by an
Independent Divers. The silt
curtain was maintained in proper condition. A temporary rock bund connected to
Bay 7 will be also constructed in mid-Jan 2012. The 24-hour turbidity monitoring data and daily SS
monitoring at C7 on the incident date onwards were reviewed and no immediate
impact on water quality was observed from the data trend. The details of the
data trend are enclosed in Appendix
5.4. Any updated
action will be follow-up and reported in the coming reporting month.
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract
No. |
Key
Construction Works |
Recommended
Mitigation Measures |
HY/2009/11 |
¡P
The portion of NPR3 are
scheduled to be completed and handover in January 2012. No construction work
related to DP3 is anticipated to be conduced in coming month. |
¡P
Submission the surrender of its
Further Environmental Permit |
HK/2009/01 |
¡P
Reclamation of HKCEC3W at the
northern side within the HKCEC Water Channel would be continued; ¡P
Dredging from CH160 to CH260 for
subsequent reclamation within HKCEC Water Channel would be resumed right
after the consent from EPD for type 3 sediment has been received; ¡P
Rockfilling from CH160 to CH260
for subsequent reclamation within HKCEC Water Channel would be commenced; ¡P
Installation of sheet pile
water channel at Dome Promenade (from CH120 to CH170) would be commenced; ¡P
Installation of sheet pile
water channel at Dome Promenade (from CH170 to CH260) would be commenced; ¡P
Mainlaying works for 4 nos. of
cooling water discharge pipes at WC landfall section (B1-3) would be
completed. And subsequent reinstatement works was anticipated to be completed
be completed; ¡P
Dredging of type 3 sediment
from CH50 to CH250 for subsequent cross-harbour watermains installation off
Tsim Sha Tsui would be continued right after the consent from EPD has been
received; ¡P
Ground treatment works for the
trenches excavation of the proposed cross-harbour watermains nos. A18/b18
would be continued and anticipated to be completed; ¡P
Installation of pipe pile wall
at sea portion would be continued and anticipated to be completed; ¡P
Thrust block construction,
concrete coating for flange joint and Rockfilling protection works would be
continued; ¡P
Works would be continued at
Zone A1-5A1, A2-3B, A3-3, A3-2A, A3-5B, A3-5B, A4-3A, A4-3B, HKCEC way
in/out, A5-5, B4-2, B4-5, B1-6 and B2-2; ¡P
GI duct laying works at Zone
A4-3A and A4-3 B would be completed; ¡P
Heading Nos. H4, H5, H7 and H13
would be continued; ¡P
Heading Nos. H4 and H13 would
be completed; ¡P
Heading No. H8 would be
commenced after its corresponding jacking pit at Zone A1-5A1 has been
excavated; ¡P
After the completion of mainlaying
works at Zone B4-2 and B4-5, mainlaying works at Zone B4-4 would be
commenced; ¡P
After the completion of
mainlaying works at HKCEC way in/out, mainlaying works at Zone B4-2A would be
commenced; ¡P
After the completion of
mainlaying works at A5-5, mainlaying works at Zone B5-2 would be commenced. |
¡P
To conform the installation and setting as in the silt
screen deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
To well maintain the mechanical
equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant that may be
in intermittent use should be shut down between work periods or should be
throttled down to a minimum ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2009/02 |
¡P
Preparation works for temporary
diversion intakes of WSD salt water pumping station and Sun Hung Kai pumping
station. ¡P
Continue operation of Tseung
Kwan O Public Fill Sorting Facility; ¡P
Continue E&M works and ABWF
works of passenger terminal; ¡P
Complete ¡P
Complete excavation works for
noise barrier 2 at Expo Drive East; ¡P
Continue slab modification for
NB 1 footing at Expo Drive East; ¡P
Continue construction for bus
shelter at Expo Drive East; ¡P
Continue trench excavation and
pipe laying works along Harbour Road; ¡P
Continue trench excavation and
deck over at Tonnochy Road; ¡P
Continue construction from +3.10mPD
to + 5.17mPD for WSD Salt Water Pumping Station; ¡P
Complete pipeline jacking WSD
intake A; ¡P
Continue construction of
seaside cofferdams for salt water intake culvert, submarine outfall and Box
Culvert N1; ¡P
Commence excavation works of
landside cofferdam for the construction of Bay 6 ¡V 10 salt water intake
culvert; ¡P
Continue backfilling rockfills
for the installed submarine outfall pipes; ¡P
Continue installation of the
temporary water diversion steel frame; ¡P
Commence the temporary internal
propping works for Box Culvert O construction; ¡P
Continue substructure works for
the New Ferry Pier |
¡P
To cover the dusty material or stockpile by impervious
sheet; ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To well maintain the mechanical equipments / machineries
to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Movable noise barrier shall be
deployed for demolition works ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HY/2009/15 |
¡P
ELS works at TS1; ¡P
Pumping test and ELS
preparation works at TPCWAE ; ¡P
Night time protection works at
CHT; and ¡P
Precautionary works at Abutment
A |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2010/06 |
¡P
Installation of bored pile
casing; ¡P
Excavation of bored piles; and ¡P
Bored Pile Concreting |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |